Soil samples will be taken on September 9th – no restrictions for the public
Preparations are underway in Darmstadt for the construction of a new primary school: A two-stream primary school Albert-Schweitzer-Anlage The building site is located between Spreestraße, Adelungstraße, Fritz-Bauer-Straße and Albert-Schweitzer-Anlage.
On Tuesday, September 9, 2025 soil samples will be taken there . This preparatory measure serves to classify the soil into disposal categories. This is to ensure that the excavated material generated during construction can be transported and disposed of quickly and in accordance with regulations.
The excavation work is expected to take one day. Immediately after the sampling, the excavated holes will be refilled and compacted. There will be no disruptions , as the work will be carried out exclusively on the meadow.
(Darmstadt - Red/PSD/DK)