Hessen Mobil announces fourth construction phase starting January 11, 2027 – Current section is scheduled to be reopened to traffic by December 21
The extensive construction work on state road L 3100 through the town of Jugenheim is entering its next phase. While the current construction phase is scheduled for completion before Christmas, work on the fourth phase will begin in January 2027 after a winter break. This phase will again require a full road closure and is expected to last until autumn 2027.
As Hessen Mobil reports, the final work on the sidewalks and supply lines is currently underway in construction section 3b between the access road to the volunteer fire department and the intersection of Bickenbacher Straße/Hauptstraße.
The asphalt work is scheduled for mid-December. According to current plans, the roadway in this area should be reopened to traffic by Monday, December 21, 2026.
The fourth construction phase begins on January 11th
Construction work is scheduled to resume on Monday, January 11, 2027, after the winter break, provided that weather conditions allow for a planned start.
The fourth construction phase extends from the intersection of Bickenbacher Straße/Hauptstraße (district road K 146) to just before the junction of the road “Im Säbchen”.
Due to the narrow road width, this section must also be completely closed to vehicular traffic for the entire construction period.
The work is expected to last until autumn 2027.
Roadway, sidewalks and utility lines will be renewed
In the fourth construction phase, Hessen Mobil will completely renew the roadway of the L 3100.
At the same time, the municipality of Seeheim-Jugenheim and the municipal utilities are continuing work on the sidewalks, canals, drinking water pipes and house connections.
Energy and telecommunications infrastructure is also being modernized. GGEW and Telekom are laying or renewing lines for electricity, gas, and fiber optics.
In addition, the municipality is modernizing the street lighting.
Another measure concerns the intersection of the L 3100 with the K 146. The traffic light system will also be renewed there as part of the construction work.
Diversion continues via the B3
The long-distance diversion via the B3 federal highway remains in place for through traffic. This means traffic will continue to bypass Jugenheim.
Pedestrian access will be maintained in the area of the closed intersection of Bickenbacher Straße and Hauptstraße. To this end, one side of the sidewalk will always remain open, or a temporary walkway will be provided.
Special attention is being paid to school routes. The municipality of Seeheim-Jugenheim has developed a specific school route plan to ensure the safe passage of schoolchildren during the construction work.
Hessen Mobil will provide separate information regarding the specific traffic regulations and the start of the fourth construction phase.
A total of 1.1 kilometers of road will be renewed
The renovation of the L 3100 in Jugenheim covers a total distance of approximately 1.1 kilometers.
The construction area begins at the southern entrance to the town and extends to the level of the Landbach stream shortly before the junction with the road “In den Pfifflergärten”.
The entire project is divided into five construction phases, each of which will require a full road closure. Current plans call for completion by the end of 2027.
During the complete reconstruction, the existing road surface is excavated to a depth of approximately 50 centimeters. A new road structure is then constructed, consisting of a frost protection layer approximately 30 centimeters thick and an asphalt surface layer approximately 20 centimeters thick.
In addition, street drains, connecting pipes and curbs will be renewed.
In the entire construction area, the municipality of Seeheim-Jugenheim is also having the sidewalks and side areas on both sides of the street repaired or completely renewed.
Total costs of approximately 5.8 million euros
A total of approximately 5.8 million euros is earmarked for the extensive road and pipeline renovation.
According to Hessen Mobil, of this amount, around 1.7 million euros will go to the state of Hesse, about 1.2 million euros to the municipality of Seeheim-Jugenheim and around 2.7 million euros to the municipal utilities.
GGEW will cover a further approximately 220,000 euros for the relocation of supply lines and media routes.
The renovation will not only renew the roadway and footpaths, but also modernize essential parts of the underground infrastructure.
The most important dates and information
Current construction phase 3b
Area: Access road for the volunteer fire department to the intersection of Bickenbacher Straße/Hauptstraße
Asphalt work: Expected mid-December 2026
Planned opening to traffic: By Monday, December 21, 2026
Fourth construction phase
Start: Monday, January 11, 2027, weather permitting
Expected duration: Until autumn 2027
Area: Intersection of Bickenbacher Straße/Hauptstraße (K 146) to just before the junction "Im Säbchen"
Traffic management: Full closure during construction work
Diversion: Via the B3
Pedestrian traffic: One side of the sidewalk will remain open or a temporary walkway will be set up
Overall measure
Route length: Approximately 1.1 kilometers
Construction phases: Five
Planned completion: End of 2027
Total costs: Approximately 5.8 million euros
Further information: Hessen Mobil
(BERGSTRASSE – RED/PM)