Since the planned works may have a significant impact on the road space, HEAG mobilo would like to inform residents, businesses, institutions and road users about the project at an early stage.
The company invites the public to an information event at the Darmstadt Clinic on Wednesday, November 25, 2026, from 6:30 p.m. to 8:30 p.m.
The event will take place in conference room 85 on the first floor of the hospital at Grafenstraße 9.
There, the project managers will present the planned measures and be available for questions and discussions with the participants.
Those interested are asked to register in advance via the HEAG mobilo project page. Further information about the project is also available there.
Registration and information: heagmobilo.de/bismarckstrasseost
The city of Darmstadt is planning further work
Parallel to the measures taken by HEAG mobilo, the city of Darmstadt is also planning changes in the eastern part of Bismarckstrasse.
Outside the bus stop areas, additional work is planned on the road surface and manholes in certain sections. The traffic signal systems will also be renewed.
The measures taken by the city and HEAG mobilo will remain organizationally and responsibilities-wise separate. However, since they affect the same road space, planning and implementation will be closely coordinated at the respective interfaces.
Construction will begin no earlier than summer 2029
It will be some time before the entire project is actually implemented. According to the current planning status, the extensive construction work cannot begin before summer 2029 at the earliest.
However, initial work on the overhead contact line system is already planned for spring 2027. In the western construction section between Dolivostraße and Kasinostraße, it will be upgraded.
In the coming years, the plans will be further specified, the construction processes will be worked out, and the necessary permits will be obtained.
It is not yet clear what traffic disruptions are to be expected during the later construction work.
The most important information
Project: Renewal of the tram infrastructure in eastern Bismarckstrasse
Planned measures: Barrier-free expansion of stops, consolidation of stops, track renewal and reinforcement of the overhead contact line system
Information session: Wednesday, November 25, 2026
Time: 6:30 p.m. to 8:30 p.m.
Location: Darmstadt Hospital, Grafenstraße 9, Conference Room 85, 1st floor
Registration: heagmobilo.de/bismarckstrasseost
Initial work: Expected to begin in spring 2027, overhead contact line system between Dolivostraße and Kasinostraße
Start of main construction work: Earliest summer 2029
(DARMSTADT – RED/HEAG/isa)